In the case of lost circulation during drilling, the use of multiple activation of bypass valve can achieve multiple high concentration, large particle plugging materials and squeezing cement plugging without pulling out of BHA.
Opening of bypass valve: before plugging operation, first pulling out of BHA to the safe well section and drop in an active ball. When the active ball is located on the ball seat, the low pump will slowly hold the pressure. When the pressure difference reaches 0.7-1.5mpa, the pressure holding pressure is greater than the spring force to make the sliding sleeve go down. When the sliding sleeve goes down to the lower limit position, the bypass hole of the sliding sleeve is aligned with the bypass hole of the upper sub, and the bypass valve is opened. Increase the displacement to the construction displacement, pump in the plugging slurry, and the plugging slurry enters the leakage layer from the bypass hole for plugging directly. When the pump is stopped, the sliding sleeve will reset under the spring force, and the bypass valve will close automatically, so as to reduce the possible U-shaped pipe effect or well control problems. When the bypass hole needs to be reopened, the pump can be operated again slowly.
Closing of by-pass valve: after the completion of plugging construction, when it is necessary to resume drilling, drop in two closed balls. When the closed ball reaches the by-pass hole, it begins to hold pressure and slowly increases the pressure. When the pressure difference reaches the designed shear pressure of the activated ball (the design pressure is 10 MPa), the activated ball is sheared and passes through the ball seat, and the activated ball and closed ball all fall into the ball basket. The sliding sleeve moves upward under the action of spring force, the bypass hole of sliding sleeve is staggered with the bypass hole of upper joint, the bypass valve is closed and drilling is resumed.
In the operation of horizontal well, directional well and highly deviated well, the use of Multiple activation bypass valve, which can realize large displacement well flushing and rock cuttings bed flushing, which not only improves well flushing efficiency, but also protects downhole instruments and tools, If necessary, open the bypass hole to clean the inner wall of casing or BOP group.
When the bypass system needs to be closed, put in two closed balls, squeeze out the locking ball by hold pressure (the design pressure of locking ball extrusion is 7MPa), and continue to hold pressure to close the bypass system.