Features Between Plug & Perf Method And Ball & Sleeve Method
Knowledge

Features Between Plug & Perf Method And Ball & Sleeve Method

2024-11-06

Cost Analysis

The most significant cost savings use of OHMS come from the saved time on location and horsepower requirements associated with the fracture treatment. Tubing Conveyed perforating, Wireline perforating and plugs are just a few of the added costs needed to perform the plug and perf procedure that are not necessary in the OHMS system. The OHMS completion method eliminated approximately two weeks of completion operations at a cost savings of $300,000 to $400,000 per well at 2005 pricing.

Additional costs for plug-and-perf operations include renting and running a tieback string to provide a mono-bore for plug and gun deployment, wireline charges, and additional pumping charges.

The cumulative effect of this delay over the course of a sustained drilling program can have a significant impact on the net present value (NPV) of the project.

For example, in the Bakken Shale an extra 200 bbl is used per stage to pump down plugs. For a 14-stage completion, the average cost for water using OHMS is US$40,000 saving 15% or $6,000 per job (Zander et al., 2010). The cumulative effect of these savings taken over the course of a sustained drilling program can have a significant impact on the net present value of the project.

Time Aspects

With no logistical issues or mechanical failures, the fracture treatment of a 20-stage OHMS (the technical limit at the time of the study) could be pumped in a single, 24-hour period. A comparable plug and perf completion can take up to five days.

An additional benefit is to greatly increase the availability and flexibility of the service company’s hydraulic fracturing treatment equipment schedule.

The shorter stimulation treatment time of OHMS completions allows for less stand-by time of frac and wireline services and also allows the well to be put on production faster than a cemented liner, plug and perf well, which maximizes usage of increasingly limited frac crews (Edwards et al., 2010; Loehoefer et al., 2010).This disparity is strictly due to the time required to pump each stage for the plug and perf method.

The plug and perf method require bridge plugs to be pumped down the tubing, which requires the wellbore to be flushed clean of all proppant to avoid getting the plug stuck before it reaches the desired setting depth which is a time consuming process.

Production Performance

The study was undertaken to compare cemented verses uncemented multi-stage fractured wells in the Barnett shale. This study analyzed the data of the two types in the same time period and the long-term production recoveries .

Previous studies in the Barnett Shale have indicated that uncemented wells perform better than cemented wells (Fisher et al., 2004). However, despite having opened other unconventional plays, the perception persists that open hole completions do not work within certain areas where cemented casing dominates (Britt and Smith, 2009).

OPTIMIZATION Scope

In terms of optimizing production of multi-stage stimulated wells, recent modeling simulations of depletion profiles from 6-stage open hole and cemented liner multi-stage completions have shown that open hole completions result in better drainage of the lateral (Themig, 2010). However, most models are unable to simulate the varying stresses in a horizontal wellbore the actual growth path and therefore size of the fracture cannot be determined. This creates a problem when attempting to optimize the fracture growth to allow for the most contact with the formation.

While the plug and perf method does seem to combat the majority of the concerns above including isolation with cement, perforations that extend into the formation to combat the hoop stress (Britt et al, 2009).But cementing off the lateral prevents the contribution of production from natural fractures and fissures often present in unconventional reservoirs that an open hole lateral would benefit from.

Operational Characteristics

The major operational advantage of OHMS completions is that they can be performed in a single, continuous pumping operation without the need for a drilling rig or wireline/CT services. This single feature provided the primary source of time and cost savings.

However the plug and perf technology required following tasks, all down hole work after the drilling rig had reached total depth (TD): cementing of the lateral casing, coiled tubing or tubing conveyed toe stage perforating, the setting of 5 or 6 bridge plugs, and perforating runs for a 6 or 7 stage hydraulic fracture treatment design. Then, after fracturing treatment, the long drill out process of bridge plugs set between stages.

Stimulation dynamics

There are differing opinions on how fractures initiate in the two systems:

The OHMS system allows for the fracture treatment to seek out the area of least principal stress along the wellbore and propagate one or multiple fractures. This method seems like a natural fit in a hard rock low perm environment, however it can lead to some problems when attempting to model the fractures.

However in Plug and Perf method concrete entry points into the formation to allow for easier fracture initiation and then propagation throughout the reservoir.

Well Downtime

Discounting fracture treatment scheduling concerns often encountered, a well completed using OHMS can be put on production within two days of rig release.

The plug and perf system can add an additional 4 days to the fracture treatment and introduce several logistical “headaches” including trucking and timing issues.

HSE factors (Health, Safety and Environment)

OHMS completions are safer due to the reduced number of trips in and out of well, reduced time on site, as well as no requirement for perforating explosives.

Best fracturing practices

Development of best fracturing practices over the last few decades would include: not over displacing proppant, ensuring near-wellbore conductivity, promoting immediate flowback, optimizing load recovery, keeping breakdown pressures low, minimizing fracture tortuosity and minimizing fluid loading (Themig, 2010)

Immediate flowback.

The importance of managing the flowback period of a well is another parameter that has been recognized as an important factor for optimum well production performance (Crafton and Gunderson, 2007). OHMS completed wells can be immediately flowed back and put on production after stimulation as opposed to requiring time-consuming drill out of bridge plugs and potential shut-in periods which can exacerbate formation damage and cause irreparable reductions to the flow rate and regained permeability.

Over-displacement

In plug and perf, to ensure that bridge plugs do not get stuck in the well due to the presence of proppant in the wellbore from the previous stage, an entire wellbore worth of fluid is displaced before a bridge plug is pumped down which although removes the extra proppant but also pushes that proppant out into the fracture away from the wellbore. On the other hand, by taking into account the type of system being run, the depths, lateral lengths and fluids being displaced, OHMS completions can more accurately place a ball on seat to isolate the previous stage’s fracture treatment resulting in the more ideal situation–proppant placed right at the wellbore reducing over displacement of the fracture treatment.

As one of the leading manufacturers of bridge plugs, Vigor offers professional customized solutions tailored to your specific site requirements. Our expertise in bridge plug technology ensures that you receive high-quality products designed to meet your unique needs. Whether it's for well abandonment, zonal isolation, or any other application, we work closely with you to deliver optimal performance and reliability. Choose Vigor for unparalleled support and innovative solutions in the oil and gas industry.